Expand capacity of the existing water production plant to 20 MGD. Work included demolition and removal of existing Sedimentation Basins, Splitter Box, Raw Water Pump Station, High Service Pumps, and Chemical Storage & Feed Facilities. Construct new Raw Water Intake Structure, Raw Water Pump Station, Raw Water Flow Control & Metering Vault, Rapid Mix Basin, Flocculation & Sedimentation Basins, High Service Pump Station, and Chemical Storage & Feed Facility. Install new Air Release Valves on distribution system. Renovate the existing Administration Building and existing Filters, and replace Filter Effluent Transfer Pumps.